Application registered
Consultation
period
Application under consideration
Decision
made
Description
Variation of conditions 5 & 6 on planning application P22/V0479/FUL - for conditions 5 and 6 to have the trigger for submission and approval delayed until prior to occupation. Conditions 3 - trees, 7 - access, 8 roofing, 9 landscape and 12 - fencing to be changed to compliance conditions once those matters are decided which should have occurred before the application is considered.
Demolition of existing buildings. Phased construction of five dwellings and associated development including gardens and parking.
Location
Andersey Farm Grove Park Drive Lockinge
Applicant
Beaumont Property Development
c/o JPPC
Agent
JPPC- Chartered Town Planners
JPPC, Bagley Croft
Hinksey Hill
OXFORD
OX1 5BD
Consultation / Notification
No further Representations on this application will be accepted.
Consultations / Notifications to date are shown below.
Name / Number
Date Sent
Response Date
Ardington and Lockinge Parish Council
c/o Dr C F Knights
7 The Rickyard
Ardington
Wantage
Oxon
OX12 8PG
Application Type
Minor
(Section 73)
Application Progress
Date Received
20th September 2022
Registration Date
20th September 2022
Start Consultation Period
4th October 2022
End Consultation Period
26th October 2022
Target Decision Date
18th November 2022
Decision
Planning Permission on 18th November 2022